Week One :
Formulate Design Ideas |
|
|
|
Sub -teams formulate
design ideas |
Mon - Sat |
1/12 - 1/17 |
|
Complete design ideas |
|
|
|
Team meeting / each
Sub-team presents design ideas |
|
|
|
Week Two : Design /
Integrate Systems and Components |
|
|
|
Sub-teams design systems
and components |
Mon - Sat |
1/19 - 1/24 |
|
Complete system designs,
component drawings and parts list |
|
|
|
Team meeting /
Presentation of designs by each Sub-team |
|
|
|
Week Three : Fabricate
/ Procure Components |
|
|
|
Components fabricated /
parts ordered |
Mon - Sat |
1/26 - 1/31 |
|
Complete component
fabrication and procurement |
|
|
|
Week Four : Assemble
Robot |
|
|
|
Sub-teams assemble robot |
Mon - Sat |
2/2 - 2/7 |
|
Complete robot assembly |
|
|
|
Week Five : Develop and
Test |
|
|
|
Develop and test robot |
Mon - Sat |
2/9 - 2/14 |
|
Complete developement and
testing |
|
|
|
Week Six : Game
Practice and Revisions |
|
|
|
Field team practices and
final revisions made |
Mon - Sat |
2/16 - 2/21 |
|
Prepare robot for shipping |
|
|
|
Week Seven : Ship Robot |
|
|
|
Ship robot |
Tues. |
2/24 |
|
Team meeting-review design
/ competition needs / competition Sub-teams |
Wed |
2/25 |
|
Fabricate spare parts for
competition
Competition in Richmond, VA at VCU |
Wed - Sat
Thurs - Sat |
2/25-2/28
3/4-3/6 |